Project Manager CBRE
Rio Tinto
Perth CBD
12,000 sqm
Engaged by CBRE, CDI undertook works across multiple floors of a multi-tenanted, occupied building, completing the project in three phases. The building had multiple contractors working simultaneously, with construction activity on 22 floors at one point. Careful planning of egress for deliveries and waste removal was critical to ensure the project met its schedule and adhered to building guidelines.
The works included highly detailed client floors that required extensive attention to detail to deliver a high-quality finish. After successfully completing the works on Level 18 safely, to a high standard, and on schedule, CDI was awarded the subsequent floors.